America RC: in the second section of the K-1 house, the slab of the ninth floor is being mounted

June 07, 2021

Real Estate Corporation RIEL carries on with America residential complex erection. In the second section of the K-1 house, the floor slab of the ninth floor is being mounted and the walls are being laid. This was reported by the service department.

It is also reported that in the first section, the arrangement of the roof has been completed, the workers have begun the installation of the ventilation, sewerage, electricity and water supply systems. In parallel, the insulation of the facade of the building is under way.

We would also like to inform you that vertical elements for parking have been built in the K-2 house, and a tower crane is being installed at K-3.

You can always get more details about the construction progress from RIEL service managers.

You can find out about the conditions for purchasing an apartment in America RC in the sales departments of RIEL Real Estate Corporation: Volodymyr Velykyi Street, 10, Rudnenska Street, 8, Levandovska Street, 12 or B. Khmelnytskyi Street, 116.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Join our social networks
Contact us in convenient way
(032) 229-55-13
Feedback
The exchange rate as of 5/2/2024 is 39.65 UAH.
Sales departments
Lviv, 10, Volodymyra Velykoho Street
© 2024  America. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.